Background

Currently, there are many renewable energy developments happening across Australia. In Queensland most is solar ( either PV or thermal) but some wind power is used in places. As these forms of renewable energy are intermittent some form of storage is needed. Storage allows supply of local load when the intermittent source is not active and also allows for supply when market conditions are optimal. In this case it is proposed to install battery storage. Battery storage will supply the amountf of energy required as per the demand in times of low generation. A 500 MW Batter storage facility exists at Wivenhoe in South-East Queensland and there are others in operation or planned accross the country.

Project Scope

You are to

1. Model the entire Australian grid and investigate the contribution of power system stabilisers to stability

2. Model the PV and 382 km 132 kV or 275 kV transmission line needed. You will need to set the voltage and the number of feeders justifying your choice.

3. Satisfy the NER rules for the PV installation

4. Size the battery storage, tune exciters and estimate PSS settings for the battery.

5. Investigate the effect on stability of having the battery storage online. In particular investigate the effects on relevant critical clearing times and rate of change of frequency (ROCOF) following disturbances. You will need to be aware of the operation of power system in particular ROCOF relays.

6. Research power quality effects of solar PV and make recommendations. This will form part of your work in assessing the connection clauses of the NER.

7. Discuss social, environmental and economic (market ) impacts of the new installation. A knowledge of the Australian electricity market is essential and will be covered in lectures.

8. Document the risks to the project completion and risks from the project. Also detail risk mitigation measures

9. Team minutes and communications must be documented. These will form part of the final report.


Currently there are many renewable energy developments happening across Australia. In Queensland most is solar ( either PV or thermal) but some wind power is used in places. As these forms of renewable energy are intermittent some form of storage is needed. Storage allows supply of local load when the intermittent source is not active and also allows for supply when market conditions are optimal. In this case it is proposed to install battery storage. Battery storage will supply the amountf of energy required as per the demand in times of low generation. A 500 MW Batter storage facility exists at Wivenhoe in South-East Queensland and there are others in operation or planned accross the country.

Project Scope

You are to

1. Model the entire Australian grid and investigate the contribution of power system stabilisers to stability

2. Model the PV and 382 km 132 kV or 275 kV transmission line needed. You will need to set the voltage and the number of feeders justifying your choice.

3. Satisfy the NER rules for the PV installation

4. Size the battery storage, tune exciters and estimate PSS settings for the battery.

5. Investigate the effect on stability of having the battery storage online. In particular investigate the effects on relevant critical clearing times and rate of change of frequency (ROCOF) following disturbances. You will need to be aware of the operation of power system in particular ROCOF relays.

6. Research power quality effects of solar PV and make recommendations. This will form part of your work in assessing the connection clauses of the NER.

7. Discuss social, environmental and economic (market ) impacts of the new installation. A knowledge of the Australian electricity market is essential and will be covered in lectures.

8. Document the risks to the project completion and risks from the project. Also detail risk mitigation measures

9. Team minutes and communications must be documented. These will form part of the final report.